Timeline & Phases
From foundation to v1.0: May through November 2026.
Four phases. Integration, evaluation and launch now run September through November so testing gets the time it needs. Open-source academic AI, v1.0 target: November 30, 2026.
Where we are now
Status as of October 15, 2026
54%Overall progress · 13/24 items complete
Phase 1
Foundation & Outreach
In progress · 4/6Phase 2
Training Pipeline & Model
In progress · 6/7Phase 3
Integration & Evaluation
In progress · 2/6Phase 4
Polish & v1.0 Launch
In progress · 1/5Current focus: E4B training is finished and HuskyBot Lite can now be downloaded. Next: recruiting testers (anyone is welcome), before/after evaluation, and meetings on Repository access and licensed datasets.
Foundation & Outreach
May 15 – May 31, 2026
~2 weeks
Progress
- Open-access papers harvested (OpenAlex, arXiv, DOAJ, Europe PMC) (Done)
- GPU compute in place: RTX 5080 workstation + RunPod account (Done)
- Outreach email drafts prepared for providers, vendors and SCSU (Done)
- HuskyBot name, Circuit Husky logo and project website (Done)
- SCSU Repository (OAI-PMH) access request with Library IT (In progress)
- Licensed dataset agreements with vendors (Not started)
Key deliverables
Training Pipeline & Model
June 1 – August 31, 2026
~13 weeks
Progress
- Base model chosen: Google Gemma 4 (E4B local, 31B cloud) with QLoRA (Done)
- Training kit through hbt14: harvest, dataset, train, chat/eval, GGUF export, Windows installer (Done)
- ~5,000-example academic dataset + 157 verified SCSU Library Q&A rows (Done)
- Open-license filter and answer-only training (Done)
- 30-step test run passed (loss 3.14 → 1.46) (Done)
- Full E4B training run on the latest kit (Done)
- 31B training run on RunPod (Not started)
Key deliverables
Integration & Evaluation
September 1 – October 15, 2026
~6.5 weeks
Progress
- Held-out eval sets: SCSU Library facts and academic tasks (Done)
- No-fabrication examples: refuses to invent citations (Done)
- Before/after evaluation of the fine-tuned model (Not started)
- RAG over SCSU Library documents and research guides (Not started)
- LibSearch / research guide integration (Not started)
- Structured testing with library staff (Not started)
Key deliverables
Polish & v1.0 Launch
October 16 – November 30, 2026
~6.5 weeks
Progress
- GGUF export and Windows installer for the downloadable model (Done)
- Hugging Face model card and open-source repository (In progress)
- Final polish on tone, safety and edge cases (Not started)
- Soft launch on the SCSU Library website (Not started)
- Launch communications with library leadership (Not started)
Key deliverables
Project start
May 15, 2026
Funds committed by
June 1, 2026
v1.0 target
November 30, 2026